Construction for the new Residences at Goldener Hirsch has been enjoying a mild winter with less snow than normal. Not as great for skiers, but quite nice for the contractors. The first of two elevator/stairway towers has been completed and the second is getting close to full height as well. The two towers reach all 5 levels of the building, plus provide access to the 6th level, which is the rooftop pool – a unique feature of this new luxury hotel property.
Highlighted recent activities on the project include:
• Poured area A stair/elevator core from L2 to L4
• Finished forming the deck for area B slab.
• Placed rebar and post tension cables for area B level 0 slab.
• Continue footing excavation in area A.
Upcoming activities include:
• Pour area A stair/elevator core from L4 to L6
• Pour area B level 0 slab
• Start forming/pouring area B level 0 walls.
• Start forming footings for area A.
• Continue footing excavation in area A.